Altamira, Brazil – Major construction on the Belo Monte Dam commenced on the Xingu River in a series of developments that took place during Brazil's New Year holidays, signaling a new phase in the Brazilian government's intentions to sidestep environmental legislation and human rights conventions to build the world's third largest hydroelectric dam in the heart of the Amazon. The project's first river blockades, known as coffer dams, currently extend into the Xingu and dry out a stretch of the river, allowing for its permanent damming. Today local protestors paralyzed construction at the dam site, affirming that resistance to the project is far from over.
Today's protests centered on Belo Monte's Pimental work site, where protestors denounced "unprecedented crimes" of the Brazilian government against the Amazon and its people. Organized by the Movimento Xingu Vivo para Sempre (Xingu Forever Alive Movement) – a grassroots coalition of social movements, indigenous groups, and NGOs – the protest included fishermen, farmers, students and other groups that are suffering the impacts of the Belo Monte Dam project.
The protestors arrived at the dam site by boat, unfurling banners in front of the coffer dams with slogans such as "Belo Monte: crime of the Federal Government", blocking the movement of workers and machinery, and paralyzing construction for over two hours. The protestors spoke peacefully with construction workers, explaining the motivations for the protest.
"Despite the criminal operations that are Belo Monte, where the Brazilian government is spending billions to devastate the Xingu while creating a situation of complete chaos among local communities, we will continue to resist this monstrosity and work to call attention of the Brazilian public and the world that this wanton destruction of the Amazon will hurt us all," said Antônia Melo, coordinator of the Xingu Vivo movement. "To take away the river is to take away the life of its people, because water is life."
The first of three coffer dams, which are earthen walls built to dry out stretches of the river to open the way for dam construction, will connect the left bank of the Xingu to Pimental Island in the middle of the river. The Norte Energia (NESA) dam-building consortium has also begun to raze the jungle on the island after receiving authorization from the federal environmental agency IBAMA to clear cut over 5,000 hectares of rainforest.
Local residents were not previously informed by the government-led NESA consortium of the impending construction of the coffer dams, initiated soon after the New Year. Instead, they were alerted by a Xingu River tinged with red mud and the thundering of dynamite exploding in construction areas.